Maryland...

MD 404:
MD 404's entire length is slated to be an expressway and in the 1960's it was
proposed to be 4-laned. The only currently completed section is the Denton Bypass.
History and Construction Schedule:
| Segment |
Activity |
| US 301 to Denton |
Access control purchase is an ongoing project and began
in 2004. Engineering underway for an upgrade to a 4-lane divided
expressway. |
| Denton Bypass |
Complete 1987 |
| Legion Rd to Double Hills Rd (1 mile) |
Construction began 2001 and was completed in December
2003. |
| Double Hills Rd to MD 16 (1 mile) |
ROW purchase began 2001. Construction will begin in
2006. |
| MD 16 to Delaware border |
Access control purchase is an ongoing project and began
in 2004. |
Junction Log:
| Junction |
Type of Access |
| MD 328 |
at-grade |
| MD 313 |
interchange |
MD 702:
This is a driveway-free expressway that was built along the ROW originally planned for I-695 before the route of that freeway was shifted further west.
History:
| Date |
Status |
| 1973 |
Freeway portion of MD 702 between US 40 and MD 150 built
as I-695 |
| July 1978 |
Freeway extension plans for MD 702 changed into plans
for a partially limited access highway |
| 1990 |
MD 702 extension opens with a speed limit of 40 mph |
| 2000 |
Speed limit raised to 45 mph |
Junction Log:
| Segment |
Type of Access |
| Old Eastern Ave |
signal |
| Middleborough Rd |
at-grade |
Sources:
C. P. Zilliacus, Mike Pruett, Kent Smith,
C.C. Slater,
Scott Kozel,
Maryland DOT, Bill Penn, John R. Cambron, Dan Moraseki, Lou Corsaro,
Corey Dukes

Last Updated: 1/17/05