Mississippi...

Glossary
US 45:
 

History:

Segment Current Status History / Future Plans
State Line to Waynesboro 4-lane Arterial ROW purchase began November 6, 1998. Construction contract awarded April 2000. Paving contract awarded July 2002. The highway was completed on November 16, 2005.
South Waynesboro Bypass (Winchester to US 84) 4-lane Expressway Construction contract awarded June 1998. Paving contract awarded April 2001. Completed June 2, 2003
North Waynesboro Bypass 4-lane Expressway Complete 2003
Waynesboro to Shubuta 4-lane Arterial Complete 2003
Shubuta Bypass 4-lane Expressway Construction contract let November 2001. Opened September 28, 2004.
Shubuta to De Soto 4-lane Arterial Construction contract awarded July 1997. Paving contract awarded March 2001. The project is now complete.
Quitman Bypass 4-lane Expressway Ribbon cutting May 15, 2001
Quitman to Clarke / Lauderdale County Line 4-lane Expressway Complete in late 1999.
Clarke / Lauderdale County Line to Meridian 4-lane Expressway. Opened in stages during the mid-1990’s.
Meridian Bypass 4-lane Freeway  
Meridian to Lauderdale 4-lane Arterial Built during the 1970’s.
Lauderdale to Scooba 4-lane Arterial Opened in stages during the early 1990’s.
Scooba to the Kemper / Noxubee County Line 4-lane Arterial Complete in 1996 or 1997.
Kemper / Noxubee County Line to Shuqualak 4-lane Arterial Complete in 1999.
Shuqualak Bypass 4-lane Expressway Complete in 1999.
Shuqualak Bypass to Macon Bypass (distance of 2 miles) 4-lane Arterial Complete in 1999.
Macon Bypass 4-lane Expressway Complete in the mid-1990’s.
Macon to Brooksville 4-lane Arterial Complete in the mid-1990’s.
Through Brooksville 4-lane Arterial Complete in late 1999.
Brooksville to Noxubee / Lowndes County Line 2-lane Highway Engineering began before 2001. This project is in the STIP for ROW purchase.
Noxubee / Lowndes County Line to Carson Rd 2-lane Highway Engineering began before 2001. ROW purchase began in 2002. This project is in the STIP for construction.
Carson Rd to 4 miles south of US 82 2-lane Highway Engineering began before 2001. ROW purchase began in 2002. This project is in the STIP for construction.
4 miles south of US 82 to US 82 2-lane Highway Engineering began before 2001. ROW purchase began in 2002. This project is in the STIP for construction.
Through Columbus 4-lane Boulevard A freeway bypass of the congested area just north of Columbus is being planned. TEA-LU included $4 million of federal funding for this project.
Columbus to Hamilton 4-lane Arterial Entire segment complete by 1997.
Hamilton Bypass 4-lane Expressway Entire segment complete by 1997.
Hamilton to 5 miles east of Aberdeen 4-lane Arterial Entire segment complete by 1997.
5 miles east of Aberdeen to Aberdeen 4-lane Expressway Entire segment complete by 1997.
Through Aberdeen 4-lane Boulevard (35 mph speed limit)  
West Aberdeen Bypass 4-lane Expressway Opened December 17, 2001.
Aberdeen to US 278 4-lane Arterial Opened December 17, 2001.
US 278 to Nettleton 4-lane Arterial Opened in early 1998.
Nettleton Bypass 4-lane Expressway  
Nettleton to Alt US 45 near Shannon 4-lane Arterial Opened in the mid-1990’s.
Shannon to Saltillo 4-lane Freeway This segment was built in stages during the 1970’s and 1980’s.
Saltillo to MS 145 north of Boonville 4-lane Expressway This project was one of the first projects to be built under the 1987 4-lane Highway Program. The corridor was built in stages and was mostly complete by the mid-1990’s. MDOT is has proposed building 3 additional interchanges along this segment, at Eculautubba Rd (west of Saltillo), at Baldwyn-Ripley Rd (near Baldwyn), and at Osborne Creek Rd (near Booneville). Engineering on the interchanges began in 2005.
Booneville to Corinth 4-lane Arterial  
Corinth Bypass 4-lane Freeway  

Junction Log:

Junction Type of Access
MS 57 Interchange under construction. This will be a partial-directional interchange to the north, and will also include a ramp from NB MS 57 to SB US 45. There will be no access from NB US 45 to SB MS 57
Expressway under construction from MS 57 to MS 145 south of Waynesboro
MS 145 South of Waynesboro at-grade
Dyess Bridge Rd (on the Waynesboro Bypass) diamond
MS 184 at-grade
US 84 cloverleaf
MS 145 North of of Waynesboro at-grade
MS 145 near De Soto folded diamond interchange
MS 511 underpass with an access road
MS 18 diamond interchange
MS 145 north end of Quitman at-grade
MS 514 at-grade
MS 145 near the Clarke / Lauderdale county line at-grade
End Expressway - Begin Freeway
MS 145 just south of Meridian diamond interchange
Causeyville Rd diamond interchange
MS 19 diamond interchange
I-20 / I-59 cloverleaf interchange
Marion-Russel Rd diamond interchange
Dale Dr half-directional / half at-grade
End Freeway - Begin Expressway
MS 16 4-way stop
MS 14 4-way stop
Alt US 45 at Brooksville half-directional to/from the south
MS 388 at-grade
Expressway proposed / under ROW purchase from MS 388 to US 82
MS 25 / MS 8 east of Aberdeen trumpet interchange
MS 25 South in Aberdeen traffic signal
MS 8 west of Aberdeen diamond interchange
US 278 / MS 41 folded diamond interchange
Alt US 45 / MS 145 at Shannon 5-ramp partial cloverleaf that favors traffic going from US 45 South to Alt US 45 South and going from Alt US 45 North to US 45 North
End Expressway - Begin Freeway
Brewer Rd diamond interchange
Verona diamond interchange
Green St (Future Corridor V / MS 6 Expressway) diamond interchange
Eason Blvd diamond interchange
MS 6 / Main St diamond interchange
Front St folded diamond interchange tied into the MS 178 interchange
MS 178 3-way directional
US 78 (Future I-22) Cloverleaf interchange
Barnes Crossing Rd diamond interchange
MS 145 at Saltillo diamond interchange
End Freeway - Begin Expressway
MS 348 diamond interchange
MS 370 diamond interchange
Baldwyn-Ripley Rd (CR 6100) traffic signal. Interchange proposed.
MS 30 West diamond interchange
MS 4 / MS 30 East diamond interchange
MS 145 at-grade
MS 356 at-grade
End Expressway - Begin Freeway
Harper Rd diamond interchange
US 72 / MS 2 West diamond interchange
Wenasoga Rd diamond interchange
MS 2 East diamond interchange

 

Alt US 45:
 

History:

Segment Current Status History / Future Plans
US 45 to Noxubee / Lowndes county line 4-lane Arterial Completed in late 1999.
Noxubee / Lowndes county line to Artesia 2-lane Highway ROW purchase began August 13, 1998. Construction contract awarded October 2001. Paving contract was let in 2004. Estimated completion is in mid 2007.
Artesia to US 82 4-lane Arterial Completed in 2001.
US 82 to West Point 4-lane Arterial Completed in the early 1990’s.
Through West Point 5-lane Boulevard  
West Point to MS 25 4-lane Arterial Opened January 19, 1999.
MS 25 to MS 8 4-lane Arterial Opened September 23, 1998.
MS 8 to Okolona Bypass 4-lane Arterial Opened June 2, 1999.
Okolona Bypass (MS 245 to US 45 / MS 145) 4-lane Expressway Completed in early 1998.

Junction Log:

Junction Type of Access
US 45 at Brookville partial-directional to/from the south
MS 388 at-grade
MS 182 overpass with access roads
US 82 diamond interchange with US 82 as the through route
MS 25 north of West Point trumpet interchange
MS 382 at-grade
MS 8 diamond interchange
MS 245 at-grade
MS 41 diamond interchange
US 45 / MS 145 at Shannon 5-ramp partial cloverleaf interchange

 

MS 48: (see MS 24)

 

US 49:
US 49 is an old expressway, the first large-scale 4-lane non-Interstate project to be built in Mississippi, from Gulfport to Yazoo City. The 4-lane highway was built by paving a second set of lines to the existing 2-lane road. Today, the older set of lanes, usually the southbound lanes, are very old and have a substandard design. In some areas, the old lanes are being reconstructed. MDOT would like to convert the entire highway to an interstate-compatible freeway, but the money for that project currently does not exist. Instead, the most congested segments will be upgraded or bypassed first.

Segment Current Status History / Future Plans
US 90 to MS 53 4-lane Boulevard A bypass is an immediate priority under Vision 21.
MS 53 to Hattiesburg 4-lane Arterial  
Through Hattiesburg 4-lane Boulevard A bypass of the segment immediately north of I-59 is an immediate priority under Vision 21.
Hattiesburg to Magee 4-lane Arterial  
Through Magee 4-lane Boulevard A bypass is an immediate priority under Vision 21.
Magee to Florence 4-lane Arterial  
Florence to Richland 4-lane Boulevard A bypass is an immediate priority under Vision 21. Vision 21 plans for the bypass to intersect with I-20 at the current MS 475 interchange.
2 miles south of I-20 to I-20 4-lane Expressway The Stack III interchange project will build a freeway for the first mile south I-20.
Along the multiplex with I-20 6-lane Freeway  
Along the multiplex with I-220 4-lane Freeway  
I-220 to Flora 4-lane Arterial  
Flora Bypass 4-lane Expressway  
Flora to Bentonia 4-lane Arterial  
Bentonia Bypass 4-lane Expressway  
Bentonia to Yazoo City 4-lane Arterial  
Through Yazoo City 5-lane Boulevard  
US 49 splits into US 49W and US 49E. US 49W continues north as an expressway.
US 61 to the Arkansas border 2-lane Highway 4-laning is a mid-range proposal under Vision 21.

History:

Date Activity
1968 The US 49 expressway between Gulfport and Florence (south of Jackson) is built
1972 The 4-lane non-expressway stretch just south of I-20 is complete
Between 1979 and 1981 Expressway from Jackson to Yazoo City is complete. The last segment to be completed was through Madison County and up to Bentonia.
May 27, 2002 Traffic signal activated at Wal-Mart in Wiggins
2004 Engineering began on a new interchange at MS 35

Junction Log:

Junction Type of Access
US 90 traffic signal
I-10 interchange
MS 53 traffic signal
Existing MS 67 at-grade
Future MS 67 (north of Saucier) trumpet interchange under construction
MS 149 Wiggins at-grade
MS 26 diamond interchange
MS 149 Wiggins at-grade
MS 13 at-grade
US 98 6-ramp partial cloverleaf
Sullivan Rd A signal will be installed
US 11 cloverleaf
MS 198 traffic signal
I-55 interchange
North Hattiesburg traffic signal
MS 589 at-grade
Existing US 84 diamond interchange
Future US 84 expressway 6-ramp partial cloverleaf favoring US 84
MS 149 Mount Olive at-grade
MS 35 interchange planned. ROW was purchased in 2003, and construction will begin in 2005.
MS 149 Mount Olive at-grade
MS 28 traffic signal
MS 545 at-grade
MS 149 Magee at-grade
Magee two traffic signals
MS 149 Magee at-grade
MS 540 at-grade
MS 13 diamond interchange
MS 469 traffic signal
I-20 interchange ("The Stack")

 

US 49-W:
 

History:

Segment Current Status History / Future Plans
Yazoo City Bypass east of MS 3 4-lane Expressway Construction and paving contract awarded July 1998.
Yazoo City Bypass west of MS 3 4-lane Expressway Construction and paving contract awarded May 1998.
Yazoo City to Silver City 4-lane Expressway The construction and paving contract was awarded in June 2001 and  the northbound lanes opened to 2-way traffic on January 13, 2004. The expressway was opened on May 19, 2004.
Silver City to Inverness 4-lane Arterial  
Inverness Bypass 4-lane Expressway  
Inverness to Indianola 4-lane Arterial A roundabout will be built at US 82, with construction starting in 2004.

North of Yazoo City, the expressway will head straight north for three miles north of existing MS 3, crossing the Yazoo River 2 miles north of MS 3, before heading northwest. It will cross the county line 2 1/2 miles south of the little northwest corner formed by the county lines. 1 mile after the county line, it will again turn north, and then go north 2 1/2 miles before heading northwest again to meet the existing expressway at Silver City.

Junction Log:

Junction Type of Access
The new alignment around Yazoo City Will include two trumpet interchanges: one at the future US 49 / US 49W / US 49E split and one at MS 3.

 

US 49-E:
 

History:

Segment Current Status History / Future Plans
Yazoo City to Sidon 2-lane Highway 4-laning is a long-range proposal under Vision 21.
Sidon to US 82 2-lane Highway Engineering began in 2004. This project is in the STIP for ROW purchase. It will be built as a 5-lane boulevard.

 

US 51:
There are two short high-speed 4-lane highway segments of US 51 in northern Mississippi.

The southern segment runs between Tie Plant and Grenada. Because this parallels I-55 a few miles to the east, the 4-lane arterial serves local traffic and, along with MS 8, acts as a spur from I-55.

The northern segment is located in Coldwater. This mile-long segment is a divided 4-lane expressway with no paved shoulders and a 45 mph speed limit. There are no driveways on the expressway, and access for the adjourning properties is provided by frontage roads. This expressway segment exists because of traffic in downtown Coldwater. I-55 carries through traffic through the area and is located less than 1 1/2 miles to the east of the US 51 expressway.

History:

Segment Activity
Grenada segment completed in 2000
Coldwater segment very old

Junction Log - Coldwater Segment:

Junction Type of Access
The only major intersection on it is Central Ave 4-way stop, which carries Scenic Route 304 to the west towards Arkabutla Lake.

 

MS 53:
Two different groups are advocating the 4-laning of MS 53. The Gulf Coast Metropolitan Planning Organization calls for a 4-lane highway from US 49 to Lizana (about 9 miles) as a long-range proposal. The Vision 21 Plan of the Mississippi Legislature calls for a larger plan, calling for a 4-lane highway from US 49 to I-59 an immediate priority.

 

MS 57:
The MS 63 expressway will become the MS 57 expressway starting at a point one mile east of the current east end of the MS 57/63 multiplex. Then, for 11 miles, it will run north paralleling existing MS 57 one mile to the east. From there it will follow the existing routing of MS 57 north to State Line. The new highway will bypass State Line to the east. It will be slightly less than a mile away from Alabama when crossing the Wayne / Greene County Line and will meet up with existing US 45 one mile north of its entrance into Mississippi.

History:

Segment Current Status History / Future Plans
US 90 to I-10 4-lane Arterial  
I-10 to Vancleave 2-lane Highway Currently working on environmental impact statement. It will most likely include a western bypass of Vancleave. Engineering work began in 2004. TEA-LU included $6 million of federal funding for this project.
Vancleave to US 98 2-lane Highway 4-laning is a long-range proposal under Vision 21.
US 98 to Leakesville 2-lane Highway There are no plans to 4-lane this segment.
Leakesville to Turkey Creek 2-lane Highway ROW purchase began September 14, 1998. Construction contract let on November 23, 2004. Paving is included in a later project of the STIP.
Turkey Creek to State Line 2-lane Highway ROW purchase began September 14, 1998. The construction contract was let on November 25, 2003. Construction will begin on March 11, 2004. Paving is included in a later project of the STIP.
State Line Bypass 2-lane Highway Construction began in 2003 and paving is included in a later project of the STIP. This will be a short freeway with interchanges at US 45 and a relocated MS 42.

 

 

Sources:
Adam Froehlig, Jake Wimberley, Billy Riddle, Mississippi DOT, Chris Lawrence, AA Roads, The Sun-Herald, Clarksdale Press-Register, Meridian Star, Natchez Democrat, Vicksburg Post, Biloxi Sun-Herald, Zachary Bugg