Segment Type of Highway
Arkansas state line to US 160 2-lane Highway (Bypass Planned)
Just north of the US 160 junction to Nixa 2-lane Expressway
Nixa to 2 miles south of US 60 4-lane Boulevard
Along the multiplex with US 60 4-lane Freeway
Sunshine St. to College St. in Springfield 4-lane Expressway
College St. in Springfield to I-44 4-lane Boulevard
I-44 to 18 km north of Springfield 4-lane Expressway
18 km north of Springfield to 9 km south of Bolivar The northbound lanes are on the old arterial alignment while the southbound lanes are on an expressway alignment.
9 km south of Bolivar to Humansville 4-lane Expressway
Humansville to Collins 2-lane Expressway (Upgrade Planned)
Through Collins Brief 2-lane Boulevard (Bypass Planned)
Collins to Clinton 4-lane Expressway
Clinton Bypass 2-lane Expressway with a short segment of 4-lane Expressway
MO 7 at Clinton to 4 miles north of MO 7 2-lane Expressway
4 miles north of MO 7 to Warrensburg 2-lane road
Through Warrensburg City Street
US 50 at Warrensburg to 3 miles north of US 50 2-lane Expressway
3 miles north of US 50 to Lexington 2-lane road
Through Lexington City Street (Bypass Under Construction)
Lexington to south end of Richmond Bypass 2-lane road (Bypass Under Construction)
Richmond Bypass (1.5 miles south of MO 210 to 2.75 miles north of MO 210) 2-lane Expressway
North end of Richmond Bypass to Polo 2-lane road
Through Polo City Street
Polo to Kingston 2-lane road
Through Kingston City Street
Kingston 5 miles north of Kingston 2-lane Expressway
5 miles north of Kingston to Hamilton 2-lane road
Through Hamilton City Street
Hamilton to Gallatin 2-lane road
Through Gallatin City Street
Along the MO 6 multiplex 2-lane Expressway
MO 6 to Coffey 2-lane road
Through Coffey City Street
Coffey to Bethany 2-lane road

History:

  • 2001-2002 – New lanes completed along Route 13 between Clinton and 2-1/4 miles north of Collins

  • 2003-2004 – New lanes added and three interchanges built between Route 83/Business 13 and Route 32 in Bolivar

  • 2003-2004 – New lanes added between Bolivar and Humansville
     

Future Improvements:

  • A 2-lane expressway is planned in the Branson West area. This 2.7-mile highway will bypass the congested area near the MO 76 junction. ROW acquisition began in January 2005 and construction is scheduled to begin in summer 2006. The highway will be widened to four lanes in the future.

  • The 2-lane expressway between Humansville and Collins will be widened to a 4-lane expressway. Construction began in fall 2004 and will be completed in early 2007.

  • A 4-lane expressway bypass of Collins is planned. Construction will begin in mid-2006 and will be completed in early 2009.

  • A 4-lane expressway bypass of Lexington is under construction. The highway should be complete by mid-June 2005. Click here to see construction pictures by Ben Prusia.

Sources:
This page was written by Eric Smith. David Herman informed me of the existence of the expressway.

Disclaimer

Last Updated: 6/5/05

Comments:
Please send any comments, suggestions, corrections, additional information or pictures about this page to: