North Carolina...
 

 

Glossary

Guilford College Rd:

Guilford College Road, between High Point and Greensboro, is being upgraded to an expressway between High Point Rd and the future Greensboro Beltway (Painters Boulevard / I-40 / I-840). Some existing driveways will be maintained on the route, but access rights will be purchased.

History and Construction Schedule:

Segment Status
High Point Rd to Mackay Rd ROW purchase began on September 27, 2001. The construction contract was awarded on February 18, 2003.
Mackay Rd to Greensboro Outer Loop ROW purchase began in September 2002. Construction will begin in 2005.

 

Henderson Outer Loop:

A new expressway is being built to the southwest of Henderson. This highway will connect to I-85 at an existing diamond interchange, but will not connect to US 1. The eastern end will be at Old County Home Rd.

History:

Date Activity
September 20, 2002 ROW purchase began
May 18, 2004 Construction contract was let

 

Hope Mills Bypass:

This expressway south of Fayetteville is under construction.

Hickory East Side Thoroughfare:

This will be a new expressway looping around the east side of Hickory, connecting I-40 to NC 127. It will connect to the proposed NC 16 expressway, which will be built from Newton to Charlotte.

History and Construction Schedule:

Segment Status
I-40 to Tate Blvd ROW purchase began on April 21, 1999.
Tate Blvd to Springs Rd ROW purchase began on April 21, 1999. The construction contract was let on July 15, 2003. Completion is slated for May 2006.
Springs Rd to NC 127 To be built after 2010.

 

Kannapolis Westside Bypass:

This new expressway will extend around Kannapolis from NC 49 at the south end to near the Cabarrus / Rowan County Line at the north end.

History and Construction Schedule:

Segment Status
NC 49 to 2 miles north of NC 49 To be built after 2010
2 miles north of NC 49 to Weddington Rd (north of US 29) ROW will be purchased in 2009. To be built after 2010.
Weddington Rd to Poplar Tree Rd ROW purchase began on December 28, 2000. The construction contract was let on May 18, 2004.
Poplar Tree Rd to I-85 ROW purchase began on December 28, 2000. The construction contract was let on February 17, 2004.
I-85 to NC 73 ROW purchase began in February 1997. Construction contract was let in August 1999. The highway was completed in July 2003.
NC 73 to Macedonia Church Rd (less than 1/2 a mile) ROW purchase began on September 30, 1999. Construction contract was let on February 18, 2003.
Macedonia Church Rd to NC 136 ROW purchase began on September 30, 1999. The construction contract was let on December 16, 2003. The project is slated for completion in December 2006.
NC 136 to Tuckaseegee Rd To be built after 2010.

 

Martin Luther King Parkway:

This is an expressway in Wilmington.

Pictures:  (click here)

 

Owen Drive Extension:
This new highway in Fayetteville will extend Owen Drive from I-95 Business (US 301) to NC 87. The western part will be an expressway on new alignment and the eastern part will widen the existing Mountain Drive to a 4-lane boulevard. Further north, Owen Drive transitions into the All-American Freeway which provides access to Fort Bragg.

History and Construction Schedule:
The contract was let in January 2005.

 

 

Sources:
John Lansford, North Carolina DOT, NCRoads.com

Disclaimer

Last Updated: 3/5/06