Wisconsin...

US 8:
US 8 is planned to be an expressway from Minnesota to US 53. The EIS will be complete in late 2004. US 8 is already a 4-lane expressway on the half-bypass of Cameron, from US 53 to CR SS / Old US 53.
History - St Croix to Cameron:
Date |
Activity |
Fall 2001 and through 2002 |
Data gathering, focus groups, public information meeting, visioning workshops, preliminary engineering and environmental evaluations |
Winter 2002-2003 |
Preliminary alternatives outlined |
Early spring 2003 |
Public information meeting |
Spring 2003 |
Final range of alternatives outlined |
April 2004 |
Draft Environmental Impact Statement (DEIS) distribution |
Summer 2004 |
Public hearing |
Late summer & fall 2004 |
Selection of recommended alternative |
December 2004 |
Final Environmental Impact Statement (FEIS) distribution |
US 10:
US 10 is being built as an expressway from Fremont to Marshfield. East of that, it is a freeway.
History:
Date |
Activity |
October 1999 |
Construction started between Waupaca and WI 49 west of Fremont |
US 12:
US 12 is an expressway east of Madison from I-39/90 to Cambridge. It is 4 lanes from Madison to North Star Rd, 1/2 mile east of CTH N (south of Cottage Grove). East of that, it is a Super-2. This is the first segment of the expressway which is planned to be extended as a Super-2 across to Elkhorn in various stages.
Construction Schedule - Lake Delton to Sauk City:
Segment |
Status |
Lake Delton to I-90/94 |
Expressway complete. |
I-90/94 to Baraboo |
Construction is expected to begin in the 2008-2010 timeframe. |
Baraboo Bypass |
As part of an agreement with local governments and other agencies, planning will not begin until 2015. |
Baraboo to Sauk City |
Part of this segment is already four lanes. |
Sauk City Bypass |
As part of an agreement with local governments and other agencies, planning will not begin until 2020. |
Construction Schedule - Sauk City to Middleton:
Segment |
Status |
Sauk City to WI 78 not including Wisconsin River Bridge |
ROW bought from August 2000 to June 2002. Construction will begin in early 2004 and be complete in late 2004. |
Wisconsin River Bridge |
ROW bought from August 2000 to June 2002. Construction began in 2002 and will be complete in November 2004. |
WI 78 to CTH KP |
ROW was bought from June 2001 to June 2003. Construction began on August 20, 2003 and will be complete in November 2004. |
CTH KP to WI 19 West |
ROW was bought from July 2000 to September 2001. Construction began in late spring 2002 and was completed in October 2003. Traffic will not be switched onto all the 4 lanes until late fall 2004 though, since it is expensive and dangerous to have short stretches of four lanes open, according to WisDOT. |
WI 19 West to CTH K |
ROW was bought from October 2000 to October 2002. Construction began in spring 2003 and will be complete in late fall 2005. |
South of CTH K, US 12 will be built as a freeway. |
It will be complete in mid-2005. |
Construction Schedule - Madison to Elkhorn:
Segment |
Status |
I-39/90 to North Star Rd |
Complete October 1998 |
North Star Rd to Fort Atkinson Bypass |
Super-2 construction will begin in 2004 |
Fort Atkinson Bypass |
Currently being studied. Construction is slated to begin in the 2010-2012 timeframe. |
Whitewater Bypass |
Construction started in 2002. The highway opened on August 5, 2005. The highway was built as a super-2 expressway, but may be expanded into a 4-lane freeway in the future. |
Whitewater to Elkhorn |
Proposed, but no time frame yet |
History - Sauk City to Middleton:
Date |
Activity |
1991 |
US 12 Study Committee provides recommendations to Wisconsin State Legislature. The recommendations were to provide a four-lane divided highway, a Middleton bypass and a second bridge crossing to Sauk City. Over half of the public written responses obtained at the public informational meeting held in 1991 favored a four-lane improvement. Another 14 percent believed that some type of improvement was required but were concerned about the long-term effects of a four-lane highway. The remaining respondents opposed a four-lane improvement and favored no improvement at all or spot up-grades to the existing two-lane roadway. |
1993 |
Public responses obtained during public informational meetings held in 1993 were similar to the 1991 written responses. US 12 project is enumerated by the state legislature, this allows WisDOT to spend funds set aside for major highway projects. |
April 19, 1995 |
Draft EIS signed. |
May 1995 |
Public hearings are held on the DEIS in Sauk City and Middleton. |
1996 |
Public hearings on Supplemental Draft EIS are held in Sauk City and Middleton. |
November 5, 1998 |
Final EIS approved by the Federal Highway Administration |
1999 |
A Memorandum of Agreement (MOA) for US 12 is signed by all the major agencies involved in the project: governor, executives of Dane and Sauk counties, secretary of Wisconsin Department of Transportation, FHWA, National Park Service, US Fish and Wildlife Service, US Environmental Protection Agency, Wisconsin Deptartment of Natural Resources and the Nature Conservancy. MOA sets framework for mitigation measures. |
March 29, 1999 |
Record of decision signed by FHWA, allowing the project to proceed. |
1999-2001 |
Final Design |
Map (click here):
Sources:
Craig Holl, Wisconsin DOT, Chris Bessert, Derron Kerr

Last Updated: 3/25/06